The Research Of Project Schedule Management Of H Company Hydro-generator Custom

Posted on:2014-01-15Degree:MasterType:Thesis
Country:ChinaCandidate:Y L XingFull Text:PDF
GTID:2249330395494319Subject:Industrial Engineering
Abstract/Summary:PDF Full Text Request
Along with the development of The Times and the progress of science andtechnology, the competition of the domestic generator manufacturing industry isincreasingly fierce, the turbine generator manufacturing industry, in particular, notonly in front of the pack and the domestic hydraulic generator manufacturers, marketof hydro-generator rest-for diverted, but also inherit the European and Americandeveloped countries have technology and capital are the strength of turbine generatormanufacturing giant to competition.These products to domestic turbine generatormanufacturing industry customized project management has brought many newchallenges, whether the owners request within the time limit, the hydro-generator tobe accomplished both in quality and quantity of custom projects, capital expendituresunder budget and, ultimately, in a large extent, this will affect enterprise’s reputationand competitiveness, Even to some extent, decided to enterprise can in the fiercecompetition in the hydro-generator in an impregnable position in the manufacturingindustry. In order to make the hydraulic power mechanism has more market appealand competitiveness, in terms of product customization project management,hydraulic generator manufacturers need to do have a lot of work, including productcustomization project schedule management is Paramount, he directly affect theproduct can finish on time delivery, this is related to the reputation of a company andthe owner’s satisfaction and success of custom will make the project schedulemanagement enterprises avoid the risk of default, because of the delay of time limitfor a project and at the same time, set up reputation in the industry and improve theproduct market competitiveness.In today’s society, the project schedule management methods have a lot of kinds,especially the schedule management method based on critical chain technology ishighly regarded and favor, but in how to use the project schedule managementdiscussion on the critical chain technology and research is not a lot, especially for aspecific company’s new project, a specific how to combine the company’s actual situation and the project’s own characteristics apply critical chain technology progressfor the project planning and schedule control research is rare. Papers aimed at aspecific company, therefore, a specific new project schedule management relatedresearch, and related research results.As A well-known manufacturer of hydro-generator, H company in A competitivemarket environment, facing the same issues, project schedule management and thecompany recently signed A turbine generator with A enterprise customization project,given the company’s traditional schedule management method based on PERT methodof defects and the insufficiency, and has been difficult to meet the needs of thecustomization project schedule management, H company more scientific andreasonable decision to choose the critical chain technology to customize the projectprogress and schedule control, first of all, the effect factors of the customizationproject schedule planning is analyzed, and then use critical chain technology toprepare the custom schedule of the project, and finally, for the custom projectschedule the execution of the relevant guarantee measures are put forward.In general, the hydro-generator custom research of project schedule management,not only can make the custom project completed on time and smooth delivery, andlater for H company product customization project schedule management provides avery valuable reference.
Keywords/Search Tags:Hydro-generator, custom items, key chains, buffer, schedule control
PDF Full Text Request
Related items